- Supply, installation, termination and VLF testing of 5200m of 22kV cabling from four 20MW hydro generators to the switchgear
- Installation of cable support infrastructure
- Removal of 50 tonne cabling from a lift shaft that extended 120m below ground
- Full thermography survey and report at completion of project
- 14-day planned shut completed 2 days ahead of schedule.
AGL – Eildon/West Kiewa Hydro Power Schemes
Cable upgrade from generators to switchgear